Input type: DC input, positive common end.
Input points: 8 points.
Enter the response time: 0.2ms the following.
Rated input voltage / current: DC24V/5mA.
Output form: transistor output, leakage type.
Output points: 8 points.
OFF leakage current: 0.1mA.
Output protection function: No.
Rated load voltage / current: DC24V/0 A9GT-BUS2SU PDF. 5A.
External connection: 1 line /1 line type.
According to the external connection mode and the external equipment input and output specifications,
Choose from a rich product lineup
A9GT-BUS2SU
Finger protection through the upper part of the terminal,
The human body will not be exposed to live parts,
Therefore, the terminal station type remote I/O module can be directly mounted to the machine tool A9GT-BUS2SU PDF. Input type: DC input, positive common end.
Input points: 8 points.
Enter the response time: 1.5ms the following.
Rated input voltage / current: DC24V/7mA.
Output form: transistor output, leakage type.
Output points: 8 points.
OFF leakage current: 0.25mA.
Output protection function.
Rated load voltage / current: DC24V/0.5A.
External connection: 3 line /2 line type.
According to the external connection mode and the external equipment input and output specifications,
Choose from a rich product lineup A9GT-BUS2SU PDF.
Finger protection through the upper part of the terminal,
The human body will not be exposed to live parts,
Therefore, the terminal station type remote I/O module can be directly mounted to the machine tool. Number of channels: RS422, 1 channel
.
Configuration of master / local station,
In addition to the other site network with different CC-Link in addition to the main station and the remote station configuration can also be the main station and the local station configuration.
A local PLC can communicate with the master station PLC and other remote workstations.
MITSUBISHI PLC online debugging.
On-line debugging is the process that will through the simulation debugging to further carry on the on-line unification to adjust.
On-line debugging process should be step by step,
From MITSUBISHI PLC only connected to the input device, and then connect the output device, and then connect to the actual load and so on and so on step by step.
If you do not meet the requirements, the hardware and procedures for adjustment.
Usually only need to modify the part of the program can be.
MITSUBISHI PLC hardware implementation
Hardware implementation is mainly for the control cabinet and other hardware design and field construction.
Design control cabinet and the operating table and other parts of the electriccal wiring diagram and wiring diagram A9GT-BUS2SU datasheet.
Electrical interconnection diagram of each part of the design system.
According to the construction drawings of the site wiring, and carry out a detailed inspection.
Because the program deesign and hardware implementation can be carried out at the same time,
So the design cycle of the MITSUBISHI PLC control system can be greatly reduced A9GT-BUS2SU datasheet.